DTEK Energy Miners Brought Two New Coal Longwalls Into Operation in March
DTEK Energy Miners Brought Two New Coal Longwalls Into Operation in March

To ensure regular coal production, DTEK Energy underground miners have already put 8 new longwalls into operation since the beginning of 2024. Two of them were brought into operation last month, in March. 

This will enable us to meet the fuel needs of thermal power plants during summer peaks and accumulate reserves for the next heating season.

"Despite the enemy's attacks on the energy sector, our task remains the same - to do everything we can to ensure the stable operation of the energy system. We realise that our TPPs will be in high demand this summer and during the next heating season. Fuel extraction for thermal generation requires rhythmicity and consistency in all processes. Launching new longwalls is the foundation for production and, accordingly, reliable operation of thermal power plants, especially during peak consumption," said DTEK Energy CEO Ildar Salieiev.

DTEK Energy underground mines are planning to bring 26 new coal longwalls into operation in 2024. Last year, the company's investments in Ukrainian coal mining assets amounted to about UAH 7 bln, almost twice as much as in 2022.


 

To read more about how DTEK Energy is preparing for and getting through the heating season follow the link: Preparing for the Autumn-Winter Season (dtek.com)

19 March 2025
News and announcements Since the Start of the Full-Scale War, DTEK Energy Has Invested UAH 28 Billion in the Restoration of TPPs and the Operation of Mines
11 March 2025
News and announcements Since the Beginning of the Year, DTEK Energy’s Mechanical Engineers Have Manufactured 2 New Roadheaders and 330,000 Spare Parts for Mines
05 March 2025
News and announcements Since the Start of the Full-Scale War, DTEK Energy Has Invested UAH 28 Billion in the Restoration of TPPs and the Operation of Mines
19 February 2025
News and announcements Since February 2022, DTEK Energy Companies Have Supplied 3,000 Tonnes of Coal and 4,500 Cubic Metres of Wood To Heat Ukrainian Defenders
14 February 2025
News and announcements In January, DTEK Energy’s Mechanical Engineers Made a New Tunnelling Machine and 150,000 Spare Parts To Support Ukrainian Mines
12 February 2025
News and announcements DTEK Energy Has Employed Almost 4,000 Displaced People Since the Start of the Full-Scale Invasion
05 February 2025
News and announcements DTEK Energy Coal Miners Put the First Two Longwalls Into Operation This Year
21 January 2025
News and announcements In 2024, DTEK Energy’s Mechanical Engineers Produced 1 Million Spare Parts and 11 New Shearers To Support Ukrainian Coal Production
16 January 2025
News and announcements In 2024, DTEK Energy’s Power Engineers Rebuilt TPPs From Scratch More Than 20 Times After Massive Shelling
15 January 2025
News and announcements In 2024, DTEK Energy Invested About UAH 11 Billion in the Rehabilitation of TPPs and Operation of the Mines