Home page News Press Releases In January, TPPs of DTEK Energy increased electricity output by 12% to support the Ukrainian power grid
In January, TPPs of DTEK Energy increased electricity output by 12% to support the Ukrainian power grid
Thermal power generation02 February 2024
In January, TPPs of DTEK Energy increased electricity output by 12% to support the Ukrainian power grid

In the middle of the heating season, DTEK Energy's flexible capacities continue to support the reliability of the Ukrainian power grid, especially during peak demand.

Last month, thermal power plants of DTEK Energy supplied almost 1.5 billion kWh of electricity. This is 12% more than in January 2023 and is equivalent to the average energy consumption of about half a million households over the course of a year

“Despite regular and systematic attacks by the enemy on one of our frontline power plants, power engineers continue to do their best to maintain reliable operation of thermal generation and the power grid. Last year, our thermal power plants managed to generate 15.2 billion kWh of electricity for the grid. We repaired 25 TPP units as part of the annual scheduled maintenance campaign and restored 9 after the shelling. Since the beginning of the year, we have not slowed down and continue to produce electricity that is so important for the country. All for one purpose - to keep Ukrainians supplied with electricity and heat,” said Ildar Salieiev, CEO of DTEK Energy.

 

 

To read more about how DTEK Energy is preparing for and getting through the heating season follow the link: Preparing for the Autumn-Winter Season (dtek.com)

13 November 2024
News and announcements Year to date, DTEK Energy miners have commissioned 18 new longwall coal faces to ensure a more reliable supply of fuel to TPPs during the heating season
05 November 2024
News and announcements Year to date, DTEK Energy has invested UAH 2.6 billion in repairs and restoration of its TPPs
25 October 2024
News and announcements Since the beginning of the year, DTEK Energy's mechanical engineers have produced 760,000 spare parts and 10 new shearers to support Ukrainian coal production
15 October 2024
News and announcements DTEK Energy Fulfils All Plans To Prepare for the Heating Season
11 October 2024
News and announcements DTEK Energy Miners Put 16 New Coal Longwalls Into Operation To Ensure Consistent Fuel Supply to TPPs in Winter
10 October 2024
News and announcements Oleksandr Fomenko Is Appointed CEO of DTEK Energy
08 October 2024
News and announcements DTEK Energy Invests Over UAH 2.3 Bln in Repairs and Rehabilitation of TPPs To Ensure a More Reliable Heating Season
24 September 2024
News and announcements Year to Date, DTEK Energy’s Mechanical Engineers Have Manufactured 10 New Shearers and 683 Thousand Spare Parts To Support Ukrainian Coal Production
19 September 2024
News and announcements Power Engineers for the First Time Showed Kyiv Residents How TPP Equipment Looks After Russian Strikes
11 September 2024
News and announcements DTEK Energy Miners Put 14 New Longwalls into Operation Since the Beginning of the Year, 12 More Planned