Home page News Press Releases On the Eve of the Heating Season, DTEK ENERGY Allocated UAH 1.7 Billion to the TPP Repair Campaign
On the Eve of the Heating Season, DTEK ENERGY Allocated UAH 1.7 Billion to the TPP Repair Campaign
Thermal power generation18 October 2021
On the Eve of the Heating Season, DTEK ENERGY Allocated UAH 1.7 Billion to the TPP Repair Campaign

To ensure reliable and uninterrupted operation of thermal power plants, especially during the heating season, within 9 months this year, DTEK ENERGY allocated almost UAH 1.7 billion for the repair of TPP units, BOP, buildings and structures (according to preliminary data).

To date, power engineers have conducted 23 out of 28 scheduled (including additional) repairs of power units of thermal power plants this year. Thus, 82% of the planned volume of the repair has been completed. Corresponding work was carried out at units of Kryvorizka, Prydniprovska, Zaporizka, Kurakhivs’ka, Luhanska, Burshtynska, Dobrotvirska and Ladyzhynska TPPs.

5 units are being repaired at Zaporizka, Kurakhivs’ka, Luhanska, Dobrotvirska and Ladyzhynska TPPs.

One more repair of power units at Burshtynska TPP is scheduled by the end of the year.

‘The country is preparing for the heating season, so the task of each participant in the energy market is to do its utmost to prepare for winter. DTEK ENERGY load-following capacities have repeatedly supported the Ukrainian power system, operating at maximum and smoothing out peak periods of electricity consumption. This is especially important during the heating season. Therefore, despite the difficult situation on the market, we are investing in the repair of equipment at thermal power plants in order to minimize any interruptions in operation and ensure the stable operation of TPPs and the entire energy system,’ said Ildar Salieiev, DTEK ENERGY CEO.

In total, by the end of 2021, DTEK ENERGY plans to allocate over UAH 2.5 billion for TPP repairs.

13 November 2024
News and announcements Year to date, DTEK Energy miners have commissioned 18 new longwall coal faces to ensure a more reliable supply of fuel to TPPs during the heating season
05 November 2024
News and announcements Year to date, DTEK Energy has invested UAH 2.6 billion in repairs and restoration of its TPPs
25 October 2024
News and announcements Since the beginning of the year, DTEK Energy's mechanical engineers have produced 760,000 spare parts and 10 new shearers to support Ukrainian coal production
15 October 2024
News and announcements DTEK Energy Fulfils All Plans To Prepare for the Heating Season
11 October 2024
News and announcements DTEK Energy Miners Put 16 New Coal Longwalls Into Operation To Ensure Consistent Fuel Supply to TPPs in Winter
10 October 2024
News and announcements Oleksandr Fomenko Is Appointed CEO of DTEK Energy
08 October 2024
News and announcements DTEK Energy Invests Over UAH 2.3 Bln in Repairs and Rehabilitation of TPPs To Ensure a More Reliable Heating Season
24 September 2024
News and announcements Year to Date, DTEK Energy’s Mechanical Engineers Have Manufactured 10 New Shearers and 683 Thousand Spare Parts To Support Ukrainian Coal Production
19 September 2024
News and announcements Power Engineers for the First Time Showed Kyiv Residents How TPP Equipment Looks After Russian Strikes
11 September 2024
News and announcements DTEK Energy Miners Put 14 New Longwalls into Operation Since the Beginning of the Year, 12 More Planned