Press Releases
11/12
DTEK Energy’s TPPs supplied over 13.6 billion kWh of electricity to maintain the reliability of the grid
09/12
DTEK Energy has invested over UAH 3.4 billion in TPP repairs to ensure reliable operation of thermal generation during the heating season
08/12
DTEK Energy commissioned two TPP power units after scheduled repairs
08/12
Russia has attacked DTEK Energy’s frontline thermal power plant for the third time in 24 hours
07/12
Russia shelled DTEK Energy’s frontline thermal power plant for many hours
06/12
On the flip side of the issue: how are preparations of the power system proceeding for the winter period
06/12
Russia has once again attacked one of DTEK Energy’s frontline thermal power plants
27/11
Amid the bad weather, DTEK Energy power engineers have commissioned another Thermal Power Plant power unit and reconnected it to the energy system after scheduled repairs
27/11
Russia has shelled one of DTEK Energy’s frontline TPPs for the fifth time in a month
24/11
DTEK Energy has imported more than 100,000 tonnes of coal to Ukrainian Thermal Power Plants
23/11
DTEK Energy returned three TPP units to the power grid after short-term repairs overnight
16/11
DTEK machine builders manufactured 14 harvesters and almost 1 million spare parts to support Ukrainian coal extraction