DTEK Zaporizka TPP is now providing 230 MW to the power grid.
DTEK Zaporizka TPP has fully restored its operation after the an emergency shutdown of Unit No.3.
Earlier, Unit No.2 was started up, and at 06:59 am, the power grid operator requested that Unit No.4, too, go online to meet the evening peak power demand. Now the units are ramping up their output.
Unit No. 3, which was the only unit operating in the morning and was tripped by the turbine valve protections, is under repair. The cause of the tripping has been established, and power plant engineers are working to eliminate it.