some-alt
Home page Our business Electricity generation PJSC «DTEK Skhidenergo» Investment programmes

LIST OF DEVELOPED HEAT SUPPLY INVESTMENT PROGRAMMES AT DTEK KURAKHIVSKA TPP

Year Status Resolution Measures Description Execution
2016 Approved No. 1887 dated 27.10.2016  Replacement of the heat network section at Sobornyi avenue, Kurakhove using preinsulated pipes.  In progress
Installation of heat meters in multi-apartment buildings in Kurakhove. In progress
Development of project documentation for installation of heat meters in Kurakhove
2017 Approved № 1130  від 14.09.2017 р. Replacement of distribution line of the heat network in urban district Yuzhny, Kurakhove using preinsulated pipes. In progress
2018 Under discussion Х Х Х